SCHEDULE OF REQUIRED INSPECTIONS
SCHEDULE OF REQUIRED INSPECTIONS

NEW CONSTRUCTION OR ADDITIONS

1.  Footing Inspection - when forms are in place
2.  Footing drains
3.  Foundation and coating - before backfilling
4.  Mechanical and framing inspection - must be made before work is covered
  • Rough framing
  • Rough electrical
  • Rough plumbing
5.  Insulation inspection
6.  Final inspection and Certificate of Occupancy (CO) must be obtained before building in occupied


REMODELING

1.  Mechanical and framing inspection - must be made before work is covered
  • Rough framing
  • Rough electrical
  • Rough plumbing
2.  Insulation inspection


POOLS

1.  Footings, grounding, electric/trench, fence and alrams at final inspection

SHEDS

1.  Footing
2.  Framing
3.  Electrical (if needed)
4.  Final inspection